
Two data center projects died this month, in states with nothing in common, for reasons that look unrelated until you put them side by side.
Per the Star Tribune, Amazon suspended its planned campus in Becker, Minnesota after state lawmakers and the governor agreed to eliminate the sales tax exemption on electricity for data centers. The exemptions on computers, servers, software, cooling and energy equipment all survived. One line came off the table and the project came off with it. Amazon said its permitting and utility-agreement timelines had become "more uncertain."
Per WSLS and Cardinal News, Franklin County, Virginia's "Project Flash" was dropped on August 17 after months of community opposition. A supervisor confirmed the decision but wouldn't say why. Per the Roanoke Times, a county official resigned abruptly two days after disclosing the project's demise.
The subsidy wasn't a sweetener. It was the deal.
Everyone assumed these projects were being sited for power availability, fiber, and land. Minnesota just ran the experiment. It kept every equipment exemption and removed only the one on electricity — and the hyperscaler left.
That tells you the site selection was never primarily about the county. It was about the spread between what the campus pays for power and what everyone else pays. Narrow the spread and the map redraws.
Which is worth holding next to what we covered on August 26: Texas is now auditing the attestations behind its interconnection queue because it doesn't believe the demand is real, and Wood Mackenzie put the phantom share at 72% of 1,066 GW requested. A project that evaporates when one tax line changes was never load. It was an option someone was holding for free.
The scale is bigger than two towns
Per the Data Center Watch Q1 2026 report, covered by NBC News, at least 75 projects worth about $130 billion were blocked or delayed in the first quarter of 2026 — described as the largest single-quarter concentration on record, roughly matching all of 2025 in three months.
Organized opposition groups rose from 396 at the end of 2025 to 833 by March, spanning 49 states. More than 300 state-level data center bills were introduced in the first six weeks of the year, and statewide moratorium proposals were filed in 14 states on a bipartisan basis.
The contradiction worth preserving
This is where most coverage overreaches, so here's the honest version.
"Blocked or delayed" is not "cancelled." A project delayed by a zoning fight often reappears one county over. SemiAnalysis has publicly argued that the cancellation framing circulating this year overstates what's actually happening to US capacity, and they're a serious source making a serious point.
Both things can be true: a record quarter of local resistance, and an industry that reroutes around it faster than a county can hold a hearing. What's genuinely new in August isn't that opposition exists — it's that two projects died for reasons that had nothing to do with a zoning board. One died over a tax line item. The other died quietly, with no stated reason and a resignation attached.
What a county actually holds afterward
This is the part nobody publishes, and it's where the last two weeks connect.
When a county courts a data center, it usually rezones land, negotiates an abatement, and its utility begins planning substation and transmission capacity to serve the announced load. Rezoning is close to a one-way door — an industrial parcel does not return to the housing pipeline on its own. The abatement writes down the tax base that schools and services run on. And the grid capital, once approved, enters the rate base and earns a regulated return for thirty to forty years.
Then the project leaves. The land is still industrial. The steel is still in the rate base. The jobs never arrive. Becker, Minnesota is a town that already lost a coal plant's tax base and was counting on this to replace it.
That's the asymmetry: the developer's option was free to hold and free to abandon. The county's preparations were neither.
What this means depending on where you sit
If you live in a county courting a data center: ask two questions at the public hearing that almost never get asked. What happens to the rezoning if the project withdraws — does the parcel revert? And is there a clawback on the abatement tied to actual jobs and actual load delivered, not to announcement? A deal without both is an option written in the county's favor and exercised at the developer's.
If you own land or build housing nearby: an announced data center reprices land around it immediately and a withdrawn one does not reprice it back. If you're underwriting acquisition on a corridor thesis, the thesis needs a named project with a signed utility agreement behind it, not a press release.
If you're an investor in the corridor metros: watch which projects survive a subsidy change. Minnesota just gave you a clean test of whether a given campus was sited for fundamentals or for the tax spread, and other legislatures are watching the same result.
If you're a local official: the resignation in Franklin County is the detail to sit with. These deals are negotiated under NDA, disclosed late, and the political cost lands on whoever says it out loud. Structure the disclosure timeline before you structure the incentive.
The pattern
Two weeks ago the question was whether the demand in the interconnection queue was real. This week gave a partial answer from the other direction: a project that exits over one repealed exemption was never load in the first place. It was a low-cost option on a subsidy, and the counties treated it as a commitment.
The scoreboard so far is 75 projects and $130 billion blocked or delayed in a single quarter, opposition groups doubling to 833 across 49 states, and two August exits with no zoning fight in the causal chain at all. The industry will reroute — SemiAnalysis is right about that. The question is what's left behind in the places it routes away from, and nobody is keeping that ledger.
What to watch from here: whether any state attaches a clawback to a data center abatement this fall, and whether other legislatures copy Minnesota's electricity exemption repeal now that they've seen what it does.
The 90-day marker (tracked)
Claim: By November 30, 2026, at least three additional US counties or municipalities will formally cancel, withdraw, reject, or see abandoned a proposed data center project with an announced value of $1 billion or more — and at least one additional state will move to repeal or narrow a data center tax exemption following Minnesota's electricity-exemption decision.
Stated confidence: 70% · Verification date: November 30, 2026 · Status: OPEN
Send me one market, one deal, or one address
This newsletter is the free version of what I do: take a number everyone is repeating, find out whether it holds, and show the work.
The paid version is that same check on your numbers. For this week's question, send me the parcel or the corridor and I'll come back with the project's actual status — rezoning terms, abatement and clawback language, and where it sits in the interconnection queue — so you know whether you're underwriting a commitment or somebody's free option.
You get a written answer with the sources, the arithmetic, and an explicit list of what I could not verify. Same discipline as the tracked prediction above: a claim, the evidence, and no confidence I haven't earned.
cokas.io — written scope back in 48 hours. No sales call, ever.
Every prediction in The Pattern Brief carries a verification date and is revisited in a future edition — including this one.
