Nov 18, 2026
On August 27, in edition 046, we predicted that by November 30 at least three more U.S. counties or towns would formally reject, or see withdrawn or abandoned, a data center project worth $1 billion or more, and that at least one more state would move to repeal or narrow a data center tax break. We put that at 70%.
We can document two rejections where a $1 billion value is on the record. We found four more local defeats with no $1 billion figure in the reports we read, so they do not count under our own rule. And no state we could check has repealed its exemption.
Then, on November 3, voters did something we did not predict at all. At least 42 jurisdictions approved ballot measures to ban or restrict data centers, according to Octus, which tracked 55 measures.
The two that count
Coweta County, Georgia. On October 20, commissioners voted 3-2 to return the 323.9-acre site of CyrusOne's "Project Peach" to rural conservation zoning, per American Buildout, which cites the county's meeting record. The applicant had put the project at $1 billion in construction value, not counting servers. The county did not need a new argument. Its 2025 approval carried conditions with dates: a power agreement, already extended by twelve months, and a land disturbance permit by October 16, 2026. Neither was met, and a reversion hearing had been scheduled a year in advance.
DeSoto County, Florida. On October 27 and again on October 28, commissioners declined to rezone two properties, about 238 acres and 554 acres, for DCIP Group's planned complex of more than 15 facilities, per WGCU. The developer's chief executive had estimated the first phase alone at $5 billion to $6 billion including its power plant, per the Business Observer. The county's planning director told commissioners that "there were no operational details of the project provided to us."
The four that don't, under our own rule
Archbald, Pennsylvania. Council voted 7-0 on October 21 to deny the 14-building Wildcat Ridge campus after nine hearings, per WVIA. Residents expect an appeal. No project value appears in the report.
Frederick County, Virginia. Supervisors unanimously denied the 72-acre Winchester Gateway campus on October 28, and a second developer withdrew its rezoning request the week before, per The Virginia Pulse. The county had already removed data centers as an allowed use in September.
Loudoun County, Virginia. Amazon dropped its plan for four data centers on the former George Washington University campus it bought for $427 million, and agreed to donate 25 acres and rezone the rest for housing, per WTOP. The land price is on the record. A project value is not.
Natrona County, Wyoming. Prometheus Hyperscale abandoned a campus of nearly 1,000 acres on October 28 without ever filing an application, per Cowboy State Daily.
We set a rule that the value had to be announced, and we are holding to it.
The tax half: pledges, no repeal
The second half of our claim said a state would "move to repeal or narrow" an exemption. That wording can be scored either way, which makes it a badly written prediction.
On a loose reading it was met several times. Maryland's governor plans to seek repeal in the 2027 session, and Pennsylvania's House and Senate each passed repeal language this year in separate bills that were never reconciled, per a five-state tracker maintained by Joshua Phoebus and current to November 11. Nevada's governor-elect campaigned on a promise to stop awarding data center tax breaks, per Octus.
On a strict reading, meaning a change that became law, the same tracker's summary is plain: "No state repealed its data center sales tax exemption in 2026" among the five it covers. States added conditions around the exemptions instead. We will report both readings on November 30.
What the ballot did instead
The election moved faster than the county boards. Octus reports that Ohio voters passed at least 13 local measures prohibiting data center development and rejected six that would have rezoned land or allowed data centers inside village limits. Voters in Maine, Kansas, Illinois and Florida passed limits of their own. Winning candidates for governor in Texas, Georgia, Ohio, New Mexico and Nevada had campaigned on moratoriums or tighter rules.
A zoning denial stops one project. A ban, or a removed use category like Frederick County's, closes the door before the next application arrives. A moratorium only delays it.
What it means, by who you are
If you own land or homes near a proposed site: a rejection is rarely the last word. DeSoto's first 34 acres remain rezoned for the project. CyrusOne says it paid $60 million for its Coweta land, and county records do not show its next step. Price the parcel on what is permitted today, and check whether your county has passed a ban or moratorium since the listing was written.
If you sit on or lobby a county board: Coweta is the model. In August we told readers to ask whether a rezoning reverts if the project stalls. Coweta had written that answer into its approval, with dates, and enforced it by a 3-2 vote.
If you underwrite or lend on a deal that assumes the project: ask for the two documents Coweta asked for, a signed permanent power agreement and an issued site permit. CyrusOne's representative told commissioners that Georgia Power is studying pending projects to sort out "who's real, who's not." If the utility is still asking that question, your pro forma should be too.
If you pay the local utility bill: watch your state utility commission more than the zoning board. In Georgia, the two commissioners elected on November 3 have both pledged to keep data center infrastructure costs off household and small-business bills, per Octus.
The case against
"Rejected" is not "cancelled," and we said so in August. Prometheus left Natrona County while pressing ahead with a $32 billion campus elsewhere in Wyoming. Amazon gave up one site in a county where it says it has been building a partnership for 20 years. A project that loses a vote often reappears nearby, and in our view none of these votes changes how much computing the industry wants to build.
The score
The claim (edition 046): "By November 30, 2026, at least three additional US counties or municipalities will formally cancel, withdraw, reject, or see abandoned a proposed data center project with an announced value of $1 billion or more — and at least one additional state will move to repeal or narrow a data center tax exemption following Minnesota's electricity-exemption decision." Stated confidence 70%.
Status on November 18: OPEN, and behind. First half: two documented of the three required. Second half: unclear, because we wrote it loosely. No state we checked has repealed its exemption. Both halves must be true for a hit, and the first is short either way. Unless a third documented rejection arrives by November 30, this one will be scored a miss.
The 90-day marker (tracked)
Claim: Between November 19, 2026 and February 17, 2027, at least two more U.S. counties or municipalities will formally reject, revoke or see withdrawn a data center proposal whose value of $1 billion or more is stated in a news report or public record.
Stated confidence: 65% · Verification date: February 17, 2027 · Status: OPEN
What would make us wrong: developers stop filing in contested counties and move to places with no fight, so there is nothing left to reject, or boards keep denying projects whose sponsors never publish a dollar figure. We lowered the bar from three to two because our own count says three was too many.
Send me the parcel or the project
This newsletter is the free version of what I do: take a claim everyone is repeating, check it against the record, and show the work, including when the count comes up short.
If a data center has been announced near something you own, lend on or vote on, reply with the name or the address. I'll tell you what has actually been filed, what conditions are attached, and what I couldn't verify.
cokas.io — no sales call, ever.
Know someone whose county is courting a data center? Forward them this one. They can get the next edition free at thepatternbrief.com.
Every prediction in The Pattern Brief carries a verification date and is revisited in a future edition, including this one.
Sources
American Buildout, Oct 22, 2026: Coweta County 3-2 vote on Oct 20, 323.9 acres, $1 billion construction value excluding servers, missed power agreement and permit deadlines, $60 million land purchase, "who's real, who's not"; cites Coweta County meeting records
WGCU / Suncoast Searchlight, Oct 29, 2026: DeSoto County votes on Oct 27 and 28, about 238 and 554 acres, more than 15 facilities, 34 acres rezoned in March, planning director's quote
Business Observer, June 26, 2026: DCIP chief executive's estimate of $5 billion to $6 billion for the first phase including the power plant
WVIA, Oct 21, 2026: Archbald 7-0 denial, 14 buildings, nine hearings, expected appeal
The Virginia Pulse, Nov 3, 2026: Frederick County unanimous denial on Oct 28, 72 acres, second proposal withdrawn, data centers removed as an allowed use on Sept 23
WTOP, Oct 21, 2026: Amazon withdrawal in Loudoun County, four data centers, $427 million purchase, 25-acre donation, 20-year relationship
Cowboy State Daily, Oct 28, 2026: Prometheus Hyperscale withdrawal, nearly 1,000 acres, no application filed, $32 billion Uinta County campus
Octus, Nov 4, 2026: at least 42 jurisdictions approved restrictions, 55 measures tracked, Ohio results, other states' measures, governors-elect positions, Nevada tax-break pledge, Georgia commissioners' pledges
Joshua Phoebus, "What states changed on data centers in 2026," current to Nov 11, 2026: no exemption repealed in Pennsylvania, Virginia, Ohio, Maryland or Georgia; Maryland's planned 2027 repeal; Pennsylvania's unreconciled repeal bills. This tracker covers five states only
The Pattern Brief, Aug 27, 2026: the original claim and the reversion question
The counts of two and four are The Pattern Brief's own tally from the reports above. It is not a complete census of U.S. data center decisions